Listed below are a few projects in which Test & Balance services have been completed by Thermocline Corp. As you will see, Thermocline is proficient at providing services across a wide spectrum of facilities requiring detailed and accurate documentation.
DEA Southeastern Regional Laboratory Facility, Miami, Florida Date of Completion, July, 2011 Contract, Test & Balance new 1 story Laboratory Facility. Mechanical Engineer, RMF Engineering. Mechanical Contract Approx. Price, $---- Number of AHU’s 3, 60 ton average Project consisted of complete test & balancing entire lab facility. Common areas and Labs consisting of supply, exhaust & 58 lab hoods controlled with a flow tracking system.
Orlando Event Center (Amway Arena) Smoke Control, Orlando, Florida Date of Completion, July, 2011 Contract, Third Party Smoke Control Testing & Verification Mechanical Engineer, Smith Seckman Reid, Inc. Mechanical Contract Approx. Price, $---- Project consisted of Testing and Verifying four 150,000 cfm each Fan Wall Units and eight Wall Prop fans at 26,500 cfm each. We provided and independent analysis of the system and recommendations useful in providing performance to meet the design intent.
Viera Hospital, Viera, Florida Date of Completion, January, 2011 Contract, Test & Balance new 5 story Medical Center Mechanical Engineer, Tilden, Lobnitz, Cooper Mechanical Contract Approx. Price, $---- Number of AHU’s 20, Average Unit Capacity, 50.0 tons Project consisted of complete test & balance of all HVAC including public areas, operating rooms, lab facilities, isolation rooms, and patient rooms. The chilled water was provided by a satellite central plant.
Lakeside Medical Center, Belle Glade, Florida Date of Completion, Jan. 2010 Contract, Test & Balance new 3 story Medical Center Mechanical Engineer, Tilden, Lobnitz, Cooper Mechanical Contract Approx. Price, $---- Number of AHU’s 9, Average Unit Capacity, 50.0 tons Project consisted of complete test & balance of all HVAC including public areas, operating rooms, lab facilities, isolation rooms, and patient rooms.
FIT Harris Center for Science & Engineering, Melbourne, Florida Date of Completion, February, 2010 Contract, Test & Balance new 3 story Science & Engineering Facility Mechanical Engineer, Tilden, Lobnitz, Cooper Mechanical Contract Approx. Price, $---- Number of AHU’s 2 Parallel 40 ton. Project consisted of complete test & balance of all HVAC including Lab Ventilation Systems.
IRSC Crime Lab & Fire Arms Training, Fort Pierce, Florida Date of Completion, October, 2009 Contract, Test & Balance new 1 story Crime Lab & 1 story Fire Arms Training Facility. Mechanical Engineer, OCI Associates Inc. Mechanical Contract Approx. Price, $---- Number of AHU’s 1, 35 ton Project consisted of complete test & balance of all HVAC including Lab Ventilation Systems.
Health First North Expansion, Melbourne, Florida Date of Completion Phase I September 2006, Phase II August 2007. Contract, Test & Balance new 369,000 sq. ft. Medical Facility Mechanical Engineer, Tilden, Lobnitz, Cooper. Mechanical Contract Approx. Price, $---- Number of Units 22, Average Unit Capacity, 20 tons Project consisted of complete test & balance of all HVAC including public areas, operating rooms, lab facilities, isolation rooms, patient rooms, a new central chiller plant, 700 coil reheat system and over 20 fan coil units. Our duties also involved technical support of the Commissioning Agent.
Rosen’s Shingle Creek Resort Hotel & Convention Center, Orlando, Florida Date of Completion, September 2006 Contract, Test & Balance new 1600 room Hotel and 600,000 sq. ft. Convention Center Mechanical Engineer, Helman Hurley Charvat Peacock Architects, Inc., Maitland, Florida. Mechanical Contract Approx. Price, $---- Number of AHUs & RTUs Units 75, Average Unit Capacity, varied 133 Common Area Fan Coil Units 39 Kitchen Hoods Project consisted of complete test & balance of all HVAC systems.
Parrish Medical Center, Titusville, Florida Date of Completion, Jan. 2003 Contract, Test & Balance new 5 story Medical Center Mechanical Engineer, Tilden, Lobnitz, Cooper Mechanical Contract Approx. Price, $---- Number of AHU’s 17, Average Unit Capacity, 50.0 tons Project consisted of complete test & balance of all HVAC including public areas, operating rooms, lab facilities, isolation rooms, and patient rooms. The chilled water was provided by a satellite central plant and the chilled water was balanced in 2 phases.
UCF Biological Sciences Bldg. Orlando, Florida Date of Completion, Feb. 2003 Contract, Test & Balance 1 renovated 4 story & 1 new 4 story lab facility Mechanical Engineer, GRG Mechanical Contract Approx. Price, $---- Number of Units 5, Average Unit Capacity, 82.0 tons Project consisted of Testing Adjusting & Balancing the entire facility, including setting up over 40 labs & 3 BL-3 labs
Launch Complex 37, CCAFS, Florida Date of Completion, Dec. 2002 Contract, Test & Balance launch Complex and support facilities. Mechanical Engineer, Washington Group Mechanical Contract Approx. Price, $---- Number of Units 12, Average Unit Capacity, 20.0 ton Project consisted of general office areas, Vehicle cooling systems, Payload cooling systems, Extensive Temperature & Humidity testing as well as various flow and temperature simulations to achieve the requirements for the Delta IV launch vehicle and payload.
DBSC Science Building #44, Dayton Beach, Florida Date of Completion, June, 2001 Contract, Test & Balance new 2 story science building. Mechanical Engineer, TLC Mechanical Contract Approx. Price, $---- Number of Units 4, Average Unit Capacity, 45.0 ton Project consisted of Testing Adjusting & Balancing the entire facility, including Lab Ventilation Systems.
LC 39 Logistics, Kennedy Space Center, Florida Date of Completion, Feb. 1999 Contract, Replace DX RTUs with Chilled Water AHUs, and balance all down steam distribution Mechanical Engineer, Tilden, Lobnitz, Cooper Mechanical Contract Approx. Price, $---- Number of Units 6, Average Unit Capacity, 55.0 tons Project consisted of removal of the existing DX units and replace with a new chilled water units connected to the existing ductwork. A new chilled water pumping system was installed to provide chilled water to the new units. The project involved all tenant and storage areas and testing & adjusting all existing air distribution, the project was completed in 3 phases.
USDA Facility, Ft. Pierce Date of Completion, Sept. 1999 Contract, Test & Balance new lab facility Mechanical Engineer, Reynolds, Smith, Hill Mechanical Contract Approx. Price, $---- Number of Units 11, Average Unit Capacity, 100.0 tons Project consisted of Testing Adjusting & Balancing the entire lab facility, 54 labs consisting of supply air, exhaust air & lab hoods controlled with a flow tracking system.